EIA II of the most popular Evonik Degussa isofluro

2022-08-26
  • Detail

Evonik Degussa isoflurone and multi-user base project EIA secondary publicity

Evonik Degussa isoflurone and multi-user base project EIA secondary publicity

September 28, 2011

[China paint information] release unit: China Tianchen Engineering Co., Ltd.

release date: September 23, 2011

1 Description

China Tianchen engineering company (Evaluation Agency) is entrusted by Evonik Degussa special chemicals (Shanghai) Co., Ltd. (the construction unit) to carry out the environmental impact assessment of Evonik Degussa integrated isoflurone and multi-user base (phase III) project. The second information release is now made to the public in accordance with national and municipal laws and regulations. China Tianchen engineering company and Evonik Degussa specialty chemicals (Shanghai) Co., Ltd. are responsible for the authenticity of the information released at this stage. With the implementation process of the project and the implementation of environmental impact assessment, relevant information will be improved or adjusted

2、 Overview of the construction project:

(1) project name: Evonik Degussa integrated isoflurone and multi-user base (phase III) project

(2) project address: No. 68 Lianhe Road, Shanghai Chemical Industry Zone

(3) industry of the project: chemical industry

(4) project content:

Evonik Degussa integrated isoflurone and multi-user base (phase III) The project is proposed to be built in the multi-user base of Evonik Degussa special chemicals (Shanghai) Co., Ltd., plot D3 of Shanghai chemical industry zone. The total investment of the project is about 1.5 billion yuan. The main products of the project are isoflurone (IP) and isoflurone diamine (IPD). The project will construct isoflurone devices, hydrocyanic acid devices, isoflurone nitrile devices, isoflurone diamine devices Supporting utilities and multi-user base expansion phase III. The project is planned to be completed and put into operation by the end of 2013

(5) conclusion of environmental impact assessment of the project

the project is in line with national and local industrial policies and the industrial positioning of Shanghai Chemical Industry Park; The nature of the land where the project is located conforms to the overall plan of Shanghai; The construction of this project is in line with the environmental protection plan that can complete the experiments of pipe ring stiffness, ring flexibility, flattening, weld stretching and so on. The production uses clean energy, adopts foreign advanced production technology and equipment, produces less pollutants, and the solid waste is comprehensively utilized as a resource, which fully embodies the concept of clean production and circular economy; The current situation monitoring data shows that the environmental quality around the company is basically good; The prediction of the project shows that under normal production conditions, it will not cause adverse effects on surrounding sensitive targets; The maximum risk of the project is acceptable; The experiment was invalid. According to the public participation survey, no one opposed the construction of this project. This report believes that it is feasible to build Evonik Degussa integrated isoflurone and multi-user base (phase III) project in Shanghai Chemical Industry Park from the perspective of environmental protection on the premise of fully implementing pollution prevention measures, implementing sewage takeover and treatment agreement and ensuring the outsourcing treatment of hazardous solid wastes after the proposed project is put into operation

3. Environmental impact assessment document of construction project

(1) link to the simplified report

(2) review period: within 10 working days from the date of issuance of this announcement

4. The scope of soliciting public opinions

the surrounding area of the construction plot

main matters for soliciting public opinions: opinions and suggestions on environmental protection of construction projects (issues unrelated to environmental protection are not accepted)

5. Public feedback

the public can put forward valuable opinions to the environmental assessment institution and the construction unit by, fax, sending letters to the designated address, interview, etc. within 10 working days from the date of this announcement

when the public expresses their opinions, please try to provide detailed contact information so that we can feed back relevant information to you in time

6. The validity period of information release is within 10 working days from the date of this information release. The public can express their opinions on the construction and environmental impact assessment of the project by sending e-mail, fax, letter or interview to the designated address

7. Overview of the evaluation organization

(1) name of the evaluation organization: China Tianchen Engineering Co., Ltd.

(2) certificate number of the evaluation organization: National Environmental Assessment Certificate Jia Zi No. 1110

(3) address of the evaluation organization: No. 521, Jingjin Road, Tianjin

(4) contact information of the evaluation organization:

contact person: Liu Gong

:

postal code: 300400 fax if you don't know the COM port connected:

email: hghbeia@

8. Overview of the construction unit:

construction unit: Evonik Degussa specialty chemicals (Shanghai) Co., Ltd.

communication address: No. 55, Chundong Road, Xinzhuang Industrial Zone, Shanghai, Postal Code: 201108

Contact: Li Yun

:

Fax:

Copyright © 2011 JIN SHI